|
by:
Jeff Vincent, CITEC Field Engineer
Setup
Reduction is one of the tools in the lean Manufacturing toolbox.
As with all lean tools, Setup Redution focuses on eliminating
waste, increasing value-added time and increasing quality --
all of which add up to increased productivity and profitability.
Setup
is the time between the last good piece of one run (batch
or lot) to the first good piece on the next run of a different
product.
Traditionally,
this has caused production to run large lots to reduce the number
of setups performed during a shift or day. The "optimal
lot size" is determined by the point where the cost of carrying
excess inventory is more economical than incurring the cost of
setup. This is known as the Economic Order Quantity.
Traditional
production thinking goes something like this... Setup is a
difficult, time-consuming job and it requires specialized personnel.
So, if we keep setups to a minimum, we don't need as many skilled
people. It's okay if we make extra inventory because we run into
problems with the equipment once in a while. Besides, short production
runs don't apply to our business.
Setup
Reduction proponents challenge traditional production thinking.
The rationale behind Setup Reduction is:
- Manufacturers
should only produce to customer orders;
- Machines
can be idle but workers should be busy adding value;
- Production
capability should be flexible enough to meet any requirements
within its capacity.
Minimal
lot sizes are the best way to achieve these goals but the setup
time must be reduced to the shortest time possible.
Although
there is a wide spectrum of setup times, each dependent on equipment
and processes, they typically break down as follows:
| Activities |
Time
Proportion
|
| Preparation,
after process adjustments, checking of material and tools |
30%
|
| Mounting
and removing blades, tools & parts, etc. |
5%
|
| Measurements,
settings & calibrations |
15%
|
| Trial
runs and adjustments |
50%
|
These
numbers are based on traditional setup procedures -- last piece
is completed, the machine is turned over to setup people, and
setup begins. Using these percentages, approximately 80% of the
setup time is spent preparing and fine tuning.
To
see the effects of Setup Reduction, consider the following example
of a North Country manufacturer:
- Production
operates 24/7. The company has eight different products to
make and only one machine to run them.
- Production
time is 15 minutes per product with a total run time of two
hours. Customer demand is for six of each of the products,
per day, for a total of 48.
- Under
their six setups and six production run process, the company
had to build inventory and rotate their production schedule
in order to meet customer demand.
Without
changing demand, equipment or run time, how could the manufacturer
meet demand in one day's production?
The
Answer: Setup Reduction
By
reducing setup time from two hours to one, production capacity
increased by six hours. That allows them to meet customer demand
in one day's production -- a daily inventory of zero. The results:
no carrying costs, no space requirements and less scheduling
and managing.
Consider
the benefits of Setup Reduction for your company: reduced setup & total
costs; increased capacity; increased flexibiilty; quicker delivery;
reduced inventory; increased quality; and more. Can you afford
not to?
JV |